Project Updates

LEVEE/FLOODWALL SYSTEM IMPROVEMENTS PROJECT—November 21, 2018 Update

levee image Nov. 21, 2018

Improvements to the Cedar Falls levee and floodwall are nearing completion. The new levee floodwall and earthen levee sections have been raised 2 feet to the new flood protection level. All flood protections are in place but other work will continue into the spring of 2019. With the wet fall season and the flooding during the summer months, aesthetic and trail improvements will be delayed until next year.

North of 1st Street, construction will continue in the spring with the installation of precast caps, decorative lights, a new promenade, stairs, and trails. The new concrete floodwall has been constructed from the Ice House to the First Street Bridge. Until the new trail is constructed, the trail closures will remain in effect for this area.

South of 1st Street and around the Waste Water Facility, crews have finished raising the earthen levee and have finalized the construction of the plaza walls and planters near 2nd Street. In the springtime, crews will finish installing trails, stairs, and finishing the surrounding area with topsoil and seeding. Trail closures will be in effect between 1st Street and Washington Park. 

Remaining work is anticipated to be completed by June of 2019. For additional information and updates for the Levee project, sign up for e-mail notifications through “Notify Me” on the City’s web page: www.cedarfalls.com/Levee


Public Informational Meeting

to provide information on the planned levee improvements to the Cedar Falls Levee System.

Thursday, September 13, 2018 from 5:30 to 6:30 p.m.
Cedar Falls Community Center
528 Main Street, Cedar Falls, Iowa
                                                                                                                          

The City of Cedar Falls is conducting a Public Informational Meeting to discuss the planned improvements to the Cedar Falls Levee System. Information will be provided on construction related items such as the proposed timeline, initial focus areas, what the work will involve, and construction storage/equipment areas.

All interested persons are invited to attend this meeting. Doors open at 5:30 p.m. with a brief presentation at 5:45 p.m. followed by a time for questions and answers.

If you have any questions prior to the meeting or after, please notify the Cedar Falls Engineering Division at (319) 268-5161.

Matthew Tolan, EI
Civil Engineer II

City of Cedar Falls
220 Clay Street
Cedar Falls, Iowa 50613
Phone: 319.268.5164
Email: Matthew.Tolan@cedarfalls.com


LEVEE/FLOODWALL SYSTEM IMPROVEMENTS PROJECT
Week of March 12th, 2018 Update

Segment 1-2

As spring quickly approaches, construction activity around the levee will start to increase as the weather improves. Crews will be working on various parts of the Levee system in the downtown area. North of W. 1st Street, construction will continue on both sides of the Main Street Bridge. Near the Ice House Museum, crews will be installing a new sanitary pump station and sanitary line that will connect near the Little Red School House. At the old Broom Factory site, crews will start adding wall extensions near the railroad tracks. On the Eastern side of the Main Street Bridge, work is continuing on the lower retaining wall located in Peter Melendy Park. Trails in this segment will be closed. Please stay away from the construction area for safety. Heavy equipment will be moving back and forth on the closed trail.

plaza

The Levee contractor will be starting on the City’s portion of the River Place Plaza construction located near 2nd Street & State Street. This construction will include retaining walls, planter boxes, and stairs connecting to the existing trail. Trails in this segment will be closed. Please stay away from the construction area for safety. Heavy equipment will be moving back and forth on the closed trail.

•Construction traffic should be anticipated on 1st St., 2nd St., 4th St., State St., and Franklin St.
•Trail closures will be in effect from 1st to 9th Street and in Peter Melendy Park.
•Construction traffic will be crossing trails. Cross only at designated crosswalks and watch for crossing signs.


LEVEE/FLOODWALL SYSTEM IMPROVEMENTS PROJECT
Week of February 12th, 2018 Update

Lower Wall

Construction north of W. 1st Street will be continuing though winter. Installation of a new sanitary sewer line will connect near the Little Red School House. Crews recently completed placing a steel casing pipe under the railroad tracks. Work is continuing on the lower wall segment located in Peter Melendy Park. This construction will replace the existing lower retaining wall between the trail and Levee wall. Trails in this segment will be closed. For safety's sake, please stay away from the construction area. Heavy equipment will be moving back and forth on the closed trail.

map

• Construction traffic should be anticipated on 1st St., 4th St., State St., and Franklin St.
• Trail closures will be in effect from 4th to 9th Street and north of the Levee wall in Peter Melendy Park.
• Construction traffic will be crossing trails. Cross only at designated crosswalks and watch for crossing signs.


LEVEE/FLOODWALL SYSTEM IMPROVEMENTS PROJECT
Week of January 8th, 2018 Update

Ice House

Construction will be starting near the Ice House Museum. Installation of a new sanitary sewer line will be placed underneath the railroad tracks and will connect near the Little Red School House. 

Construction crews are still currently working on the lower wall segment located in Peter Melendy Park. This construction will replace the existing lower wall section located north of the Levee wall near the Main St. Bridge. Trails in this segment will be closed. Heavy equipment will be moving back and forth on the closed trail.

For safety's sake, please stay away from the construction area.

map

     •  Construction traffic should be anticipated on 1st St., 4th St., State St., and Franklin St.
     •  Trail closures will be in effect from 4th to 9th street and north of the Levee wall in Peter Melendy Park.
     •  Construction traffic will be crossing trails. Cross only at designated crosswalks and watch for crossing signs.


LEVEE/FLOODWALL SYSTEM IMPROVEMENTS PROJECT
Week of December 18th, 2017 Update

wall segment

Construction crews are currently working on the lower wall segment located in Peter Melendy Park. This construction will replace the existing the lower wall section located north of the Levee wall near the Main St. bridge. Trails in this segment will be closed. For safety's sake, please stay away from the construction area. Heavy equipment will be moving back and forth on the closed trail.


Construction on the lower wall segment located in Peter Melendy Park

  • Construction traffic should be anticipated on 1st St., 4th St., State St., and Franklin St.
  • Trail closures will be in effect from 4th to 9th street and north of the Levee wall in Peter Melendy Park.
  • Construction traffic will be crossing trails, cross only at designated crosswalks and watch for crossing signs.


LEVEE/FLOODWALL SYSTEM IMPROVEMENTS PROJECT
Week of December 11th, 2017 Update

 lower wall segment plan located in Peter Melendy Park

Due to construction delays south of the Waste Water Reclamation Facility, crews will be starting construction this week of the lower wall segment located in Peter Melendy Park. This construction will replace the existing the lower wall section located north of the levee wall near the Main St. bridge. This phase of construction is anticipated to be completed in March of 2018. Crews will also be finalizing construction around the Waste Water Reclamation Facility. This phase of construction is anticipated to be completed in April of 2018. Both construction segments will continue through the winter, weather pending.


Construction on the lower wall segment located in Peter Melendy Park

     •  Construction traffic should be anticipated on 1st St., 4th St., State St., and Franklin St.
     •  Trail closures will be in effect from 4th to 9th street and north of the Levee wall in Peter             Mendy Park.
     •  Construction traffic will be crossing trails, cross only at designated crosswalks and watch         for crossing signs.


LEVEE/FLOODWALL SYSTEM IMPROVEMENTS PROJECT
Week of December 4th,2017 Update

Levee reduced 425px

Construction of the Cedar Falls Levee Floodwall System Improvements started on               November 1st. Crews are currently working around the Waste Water Reclamation Facility constructing a new concrete floodwall. This construction will continue through the winter, weather pending, around the facility and progressing towards the south. This phase of construction is anticipated to be completed in April of 2018. .


Segment 5 475px

·   Construction traffic should be anticipated on 4th St., State St., and Franklin St. 

·   Construction traffic will also be crossing the trail, please watch for crossing signs and cross only in designated crosswalks.

·   As crews move towards the south of the Waste Water Reclamation Facility, trail closures will be in effect from 4th to 9th street.


LEVEE/FLOODWALL SYSTEM IMPROVEMENTS PROJECT
Week of October 30, 2017 Update

Construction is scheduled to begin November 1st.

The contractor will begin work on Segment 1 and 5A.

Segment 1-10-30-17

             Segment 1 – Sanitary Sewer line to the Ice House Museum

                          •       Construction Traffic anticipated on 1st Street

Segment5A-10-30-17

Segment 5A – Construction of new 2 ft floodwall East of the Water Reclamation Facility

             •   Construction traffic will cross trail. Watch for crossing signs.
             •   Construction traffic is anticipated on 4th Street, State Street and Franklin Street
             •   No street closures anticipated.


PROPOSED LEVEE AND FLOODWALL IMPROVEMENTS
(OCTOBER 2017 – MARCH 2018)

Water Reclamation Facility Area
o Construction of new floodwall.
o Construction anticipated October 2017 through April 2018.
o Construction traffic will cross the trail. Watch for crossing signs.
o Construction traffic is anticipated on 4th St., State St., & Franklin St.
o Construction traffic on Main St. is not anticipated.
o No street or trail closures anticipated.


Ice House Museum Area
o Sanitary Sewer Line
o Construction anticipated in November 2017.
o Construction traffic anticipated on 1st Street.
o Construction traffic on Main St. is not anticipated.
o Closures to the Little Red School House sidewalk and parking lot to the Ice House Museum.


South of Water Reclamation Facility
o Increase levee height two feet.
o Construction on going January 2018 through April 2018
o Construction traffic anticipated on 4th St., State St., and Franklin St.
o Construction traffic on Main St. is not anticipated.
o Trail closure from 4th St. to 9th St.


Western Homes
o Construction of new floodwall and levee expansion.
o Construction on going February 2018 – May 2018.
o Construction traffic anticipated on State St., 9th St. and Irving St.
o Access limitations to parking lot behind Western Homes & Closure of Irving St.

Levee 10-24-17




""