Posted on: October 2, 2020

Cedar Falls Weekly Construction Updates: October 2, 2020

CF Construction updates graphic

Stay updated on ongoing street construction projects! Scroll down to receive the latest news and learn what you can expect in the coming week. You can also sign up to receive construction updates (including weekly notices) straight to your email by visiting www.cedarfalls.com/notify and selecting the appropriate project. 

Construction Updates: October 2, 2020


Downtown Streetscape (project located on 2nd Street):

West 2nd St remains closed with the mainline pour completed. Additional paving on the side parking areas is now completed. Next week, Benton's and KW Electric will mobilize in to prepare the sidewalks for pavers. Meanwhile, Cunningham's crew will continue working on the alley approaches, driveways, amenity pads, and concrete edge restraint. The brick paver contractor is expecting to begin work on the W 2nd Street Sidewalks afterward. The West 2nd Street roadway will be open to traffic beginning October 5th. On October 7th, Matthias and Cardinal Construction will be setting the twig benches along the parkade.

Expected project completion date: Fall 2020

Learn more about the Streetscape project at www.cedarfalls.com/downtown

West 1st Street/Hwy 57 - Phase 2 (project located West 1st Street/HWY 57-Franklin Street to Hudson Road): 

Head-to-head traffic will continue on the south lanes between Ellen and Walnut Streets. The contractor has begun paving operations in the north lanes during the week of September 28th. The contractor will also begin median related work on Hudson Road near the 1st Street intersection. Traffic on Hudson Road and commercial entrances will be maintained throughout construction.

Expected project completion date: Fall 2021

Learn more about the West 1st Street/HWY 57 project at www.cedarfalls.com/Hwy57Expansion.

West 12th Street Reconstruction (project located West 12th - Tremont to College Streets, Walnut - 11th to 12th Streets):

West 12th Street is closed from Tremont to College Streets. Cunningham has poured half of the north side of Walnut, as well as half of the south side. They have been prepping for the other halves to be poured in both the north and south portions. PCI is going to be working on the placement of subdrain behind the wall and then backfilling the wall. 

Expected project completion date: Fall 2020

Learn more about the West 12th Street Reconstruction Project (part of the Cedar Falls annual street construction program) at www.cedarfalls.com/streetconstructionprogram. 

Cedar Falls Permeable Alley Project (project located 4th/5th Street on Tremont and Iowa, 22nd and Seerley on Tremont and Franklin):

Direction has been given to Benton's regarding a ramp being poured for the 4th/5th Alley at 514 4th Streets' back door and now we are waiting on Benton's to place rock for the parking area. After this, the project will be completed with the exception of punch list items.  

Expected project completion date: Fall 2020

Learn more about the Permeable Alley Project at www.cedarfalls.com/PermeableAlleys.

Additional 2020 Annual Street Construction Updates (all projects expected to be completed by Fall 2020):

Lilac Lane (Rownd St. to McClain Dr.), Madison Street (Valley Park to Waterloo Raod), 26th Street (Iowa Street to Tremont Street): Both Lilac Lane and Madison Drive had sod placed this week. By Monday, both of these roads will be fully open to traffic. Underground work was completed at 26th Street with the intersection and curb pours to follow next week.

Visit www.cedarfalls.com/streetconstructionprogram for more information on the 2020 Annual Street Construction Program.

Additional Construction Note: The Clay Street Drainage Project is taking place in the Alley and Park between Clay/Washington and 16th/17th Street. The area is closed. Currently, the bio-cell is 70 percent complete and Bentons has all the bio mix in and has graded the surrounded area to slope specifications. Mulch, plants, and hydro-seeding will need to be done as well. The alleyway east and west drive lanes are poured as well as the north end approach and sidewalk. Cunningham will be working on the south end sidewalk and then Benton's should be coring out the sidewalk along 16th. The other bio-cell and sidewalk along W. 15th Street remain as well. Expected to be completed Fall 2020. 

Visit www.cedarfalls.com/streetconstructionprogram for more information on the 2020 Annual Street Construction Program. 

Facebook Twitter Email

Other News in Our City News

light display

Cedar Falls Tour of Lights

Posted on: November 24, 2020
Gargabe Colleciton Fall

Thanksgiving Refuse Collection Schedule

Posted on: November 18, 2020
Thanksgiving Hours

City of Cedar Falls Thanksgiving Hours

Posted on: November 18, 2020

Leversee Road Closure

Posted on: October 21, 2020

E 2nd Street Sidewalk Closure

Posted on: October 10, 2020

Hudson Road Lane Closure

Posted on: September 23, 2020
construction updates graphic

W. 1st Street/HWY 57 Reconstruction Update

Posted on: September 22, 2020
National Night Out 2019

National Night Out Event Cancelled

Posted on: September 16, 2020
mask up graphic

Mask Up Cedar Falls

Posted on: September 11, 2020

University Avenue Waterloo Update

Posted on: August 31, 2020

W. 26th St. Road Closure

Posted on: August 26, 2020

Road Closure Notice - Walnut Street

Posted on: August 5, 2020

West 2nd Street Closure

Posted on: July 31, 2020

Madison Street Closure - Stage 2

Posted on: July 30, 2020
Downtown Streetscape Social 2

West 2nd Street Closure

Posted on: July 18, 2020

West 22nd Street Closure

Posted on: July 14, 2020

W. 26th St Closure

Posted on: July 2, 2020

West 11th Street Closure

Posted on: June 19, 2020

Cedar Falls 2020 Census Update

Posted on: June 17, 2020

2nd State Lane Closure

Posted on: June 16, 2020

City Hall Closed June 12, 2020

Posted on: June 11, 2020

Madison Street Closure

Posted on: June 1, 2020

State COVID-19 Guidelines Reminder

Posted on: May 19, 2020

W. 1st St./HWY 57 Reconstruction

Posted on: May 15, 2020

Road Rehabilitation Updates

Posted on: May 8, 2020

East 2nd St. Sidewalk Notice

Posted on: May 1, 2020

Census Update

Posted on: April 27, 2020
picture of a trail

Cedar Falls Trail Safety Reminder

Posted on: April 24, 2020

W. 11th Street Closure

Posted on: April 21, 2020

Lilac Lane Closure

Posted on: April 17, 2020

2020 Street Construction Project

Posted on: April 9, 2020

Cedar Falls Prepares for COVID-19

Posted on: March 11, 2020

2020 Construction Phase 1 Begins

Posted on: March 12, 2020
IMG_6760

Cedar Falls Special Election Date Set

Posted on: February 18, 2020
IMG_6760

Cedar Falls to Hold Special Election

Posted on: February 7, 2020
20190606_081807

Cedar Falls Crime Drops 1.63% in 2019

Posted on: January 20, 2020
Hazardous Trees

Hazardous Trees on Private Property

Posted on: January 9, 2020

Hazardous Trees on Private Property

Posted on: December 18, 2019

Found Property Items

Posted on: October 4, 2017