View the latest Cedar Falls street construction updates for the week of April 19, 2021:
Downtown Streetscape and Reconstruction Project- The brick pavers have been installed along the first 8 feet of each business along the east side of the 300 block. From that 8' out to the back of the curb along Main Street, the contractor has installed the new subdrain and conduit. They will now begin work on the concrete pads for the sidewalk amenities and curb for the miscellaneous planter beds. In approximately 1 week, the new brick pavers will begin getting installed there as well.
To learn more about the Streetscape and sign up for regular email updates, visit cedarfalls.com/downtown.
West 1st Street/HWY 57 Expansion- For the week of April 19th, the contractor will continue installing storm sewer and other underground utilities as they work on the Southwest corner of W. 1st Street (HWY 57) and Hudson Road. Head-to-Head traffic will remain on the northern lanes as crews rebuild the southern half of the intersection.
To learn more about the West 1st Street/HWY 57 Expansion and sign up for regular email updates, visit cedarfalls.com/1455/Hwy-57-W-1st-Street-Expansion-Project.
2021 Street Construction Project
Learn more about the roads involved in the 2021 Street Construction Project and sign up for regular email updates at bit.ly/cf21StConstruction.
McClain Drive- Stage 1 of McClain Drive is currently underway. All of the pavement has been removed and the contractor had begun work on the sanitary line and manhole structure at the intersection of McClain and Lilac. Once the sanitary work has been completed, the new watermain along McClain will begin getting installed.
Brandilynn Boulevard (West cul-de-sac east through the Andrea Drive intersection)- Work on Stage 1 of will commence April 21. This work will include the full removal and replacement of the concrete surface.