Beginning on Friday, October 22, the contractor will be placing the base course of the asphalt overlay on the Kaspend Place cul-de-sac. For the contractor to perform this work, the road will be temporarily closed to place this layer of asphalt. Following this base course will be the necessary manhole adjustments on Monday, October 25, with the final surface course of the asphalt to be placed on Tuesday, October 26 (weather permitting).