View the latest updates on area road construction projects in Cedar Falls for the week of May 9, 2022.
Cedar Heights Drive Reconstruction (Located at Cedar Heights and Greenhill Road):
Closure/detour: Cedar Heights and Greenhill Intersection, north and southbound Cedar Heights remains closed.
For the week of May 9, the contractor will work to wrap up the last of the remaining landscaping and paving items at the Greenhill and Cedar Heights roundabout. The temporary Huntington Road access will be closed as a second crew will continue with watermain placement across Huntington and Cedar Heights adjacent to the intersection. This closure is scheduled to last approximately one week, depending on the weather.
Get more information on the Cedar Heights Drive Reconstruction Project at www.cedarfalls.com/1630/Cedar-Heights-Dr-Reconstruction.
West Viking Industrial Park, Phase V (Located on Venture Way and Technology Parkway):
For the week of May 9, the contractor will continue with mass grading operations. As the sanitary sewer is placed, the future roadway network is starting to be defined with grading operations as crews work their way to the north. Crews will continue to increase mass grading operations as the weather allows.
Get more information on the West Viking Industrial Park Expansion at www.cedarfalls.com/1648/West-Viking-Industrial-Park-Expansion.
Cyber Lane
Final grading, sidewalk, seeding, and cleanup remain to be completed.
Union Road Recreational Trail (located at Beaver Road intersection onto Union Road)
During the week of May 9, the City is waiting on the contractor to start to work on the punch list finishing items for the project and send corrective actions for SWPPP (Stormwater Pollution Prevention Plan) to comply with federal and state stormwater regulations.
Get more information on the Union Road Recreational Trail project at https://www.cedarfalls.com/1645/Union-Road-Trail-Project.
2021 Community Development Block Grant (CDBG) Sidewalk Repair and Infill Project (Location: Bluebell Infill Location)
During the week of May 9, the contractor is waiting for the weather to clear up and the ground to dry to finish up the Bluebell infill and also work on the ramps and common pannels throughout the City. They also placed seed around driveways at the Rownd infill location and are working on erosion control.
Greenhill Road and South Main Street Intersection
Closure: Southbound traffic of Main Street on the north side of the intersection
The storm sewer on the northwest is now complete. The fence on the northeast corner is fully removed, and pavement preparation will continue on the northeast and northwest corners.
Get more information on the Greenhill Road and South Main Intersection improvements at https://www.cedarfalls.com/1572/South-MainGreenhill-Intersection-Improve.
Downtown Streetscape and Reconstruction Project Phase II
The 500 block side of the parkade, adjacent to the public library, was completed Friday, May 6. East 3rd Street (from Main to State) storm sewer is halfway installed, with the contractor continuing efforts over the next two weeks.
Get more information on the Downtown Streetscape project at https://www.cedarfalls.com/1518/Downtown-Construction.
2022 Street Construction Project
West 18th Street Phase 1 (Located from Campus Street to Drury Lane: The contractor is continuing work on the replacement of the sanitary sewer manholes and will begin the installation of the watermain by the end of next week.
Get more information on the 2022 Street Construction Project at https://www.cedarfalls.com/416/Annual-Street-Construction-Program.